50 PCE or more: a detailed construction traffic analysis may be warranted (CEQR TM Ch.22, p.22-5). Construction trips only; for a phased project, add the operational PCEs of completed portions before applying the threshold.
Peak hours
- Transit
- 405 / 200
- Pedestrians
- 441 / 200
- Transit
- 405 / 200
- Pedestrians
- 441 / 200
Transit = subway + bus + rail; pedestrians = walk + every transit rider. The 200-trip figures are reference values: CEQR TM Ch.16 Level 1 operational screening thresholds (pp.16-3 to 16-4); Ch.22 sets none for transit or pedestrians, and public FEISs commonly apply them to construction. The formal screen remains 50 PCE in the construction peak hour (p.22-5).
Hourly trips, 2028 Q2
One way, in and out of the site. Hours balanced: each column adds back to its daily total.
Vehicle trips PCE
| Auto | Taxi | Truck | Total | ||||||
|---|---|---|---|---|---|---|---|---|---|
| Hour | In | Out | In | Out | In | Out | In | Out | Total |
| 6–7 AMAM peak | 375 | 0 | 8 | 8 | 50 | 50 | 433 | 58 | 491 |
| 7–8 AM | 42 | 0 | 1 | 1 | 20 | 20 | 63 | 21 | 84 |
| 8–9 AM | 0 | 0 | 0 | 0 | 20 | 20 | 20 | 20 | 40 |
| 9–10 AM | 0 | 0 | 0 | 0 | 20 | 20 | 20 | 20 | 40 |
| 10–11 AM | 0 | 0 | 0 | 0 | 20 | 20 | 20 | 20 | 40 |
| 11 AM–12 PM | 0 | 0 | 0 | 0 | 20 | 20 | 20 | 20 | 40 |
| 12–1 PM | 0 | 0 | 0 | 0 | 20 | 20 | 20 | 20 | 40 |
| 1–2 PM | 0 | 0 | 0 | 0 | 10 | 10 | 10 | 10 | 20 |
| 2–3 PM | 0 | 0 | 0 | 0 | 10 | 10 | 10 | 10 | 20 |
| 3–4 PMPM peak | 0 | 375 | 8 | 8 | 5 | 5 | 13 | 388 | 401 |
| 4–5 PM | 0 | 42 | 1 | 1 | 5 | 5 | 6 | 48 | 54 |
| 5–6 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Daily | 417 | 417 | 18 | 18 | 200 | 200 | 635 | 635 | 1,270 |
Transit trips persons
| Subway | Bus | Rail | Total | ||||||
|---|---|---|---|---|---|---|---|---|---|
| Hour | In | Out | In | Out | In | Out | In | Out | Total |
| 6–7 AMAM peak | 225 | 0 | 72 | 0 | 108 | 0 | 405 | 0 | 405 |
| 7–8 AM | 25 | 0 | 8 | 0 | 12 | 0 | 45 | 0 | 45 |
| 8–9 AM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 9–10 AM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 10–11 AM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 11 AM–12 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 12–1 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 1–2 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2–3 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3–4 PMPM peak | 0 | 225 | 0 | 72 | 0 | 108 | 0 | 405 | 405 |
| 4–5 PM | 0 | 25 | 0 | 8 | 0 | 12 | 0 | 45 | 45 |
| 5–6 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Daily | 250 | 250 | 80 | 80 | 120 | 120 | 450 | 450 | 900 |
Pedestrian trips persons, walk plus every transit rider
| Walk | Transit riders | Total | |||||
|---|---|---|---|---|---|---|---|
| Hour | In | Out | In | Out | In | Out | Total |
| 6–7 AMAM peak | 36 | 0 | 405 | 0 | 441 | 0 | 441 |
| 7–8 AM | 4 | 0 | 45 | 0 | 49 | 0 | 49 |
| 8–9 AM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 9–10 AM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 10–11 AM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 11 AM–12 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 12–1 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 1–2 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2–3 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3–4 PMPM peak | 0 | 36 | 0 | 405 | 0 | 441 | 441 |
| 4–5 PM | 0 | 4 | 0 | 45 | 0 | 49 | 49 |
| 5–6 PM | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Daily | 40 | 40 | 450 | 450 | 490 | 490 | 980 |
Daily trips, 2028 Q2
1,000 workers and 100 trucks a day · auto and taxi occupancy 1.20 · truck PCE 2.00
| Mode | Share | Person trips | Trips used | Rule |
|---|---|---|---|---|
| Auto | 50.0% | 1,000 | 834 vehicles | EVEN(ROUND(P ÷ occupancy)) |
| Taxi | 1.0% | 20 | 18 vehicles | EVEN(ROUND(P ÷ occupancy)) |
| Subway | 25.0% | 500 | 500 persons | EVEN(P) |
| Bus | 8.0% | 160 | 160 persons | EVEN(P) |
| Rail | 12.0% | 240 | 240 persons | EVEN(P) |
| Walk | 4.0% | 80 | 80 persons | EVEN(P) |
| Trucks | 400 PCE | 2 × ROUND(trucks × PCE) |
Quarterly increment
| Quarter | WA workers | WA trucks | Workers counted | Trucks counted | Worker vehicles + truck PCE |
|---|---|---|---|---|---|
| 2027 Q1 | 150 | 60 | 150 | 60 | 182.5 |
| 2027 Q2 | 300 | 80 | 300 | 80 | 285.0 |
| 2027 Q3 | 450 | 100 | 450 | 100 | 387.5 |
| 2027 Q4 | 600 | 90 | 600 | 90 | 430.0 |
| 2028 Q1 | 800 | 100 | 800 | 100 | 533.3 |
| 2028 Q2peak | 1,000 | 100 | 1,000 | 100 | 616.7 |
| 2028 Q3 | 900 | 80 | 900 | 80 | 535.0 |
| 2028 Q4 | 700 | 60 | 700 | 60 | 411.7 |
| 2029 Q1 | 450 | 40 | 450 | 40 | 267.5 |
| 2029 Q2 | 200 | 20 | 200 | 20 | 123.3 |
During the operational peak periods
For the overlap check in CEQR TM p.22-5. A period starting on the half hour is the mean of the two clock hours it spans.
| Period | PCE in | PCE out | PCE total | Transit | Walk | Pedestrians |
|---|---|---|---|---|---|---|
| 8:00–9:00 | 20 | 20 | 40 | 0 | 0 | 0 |
| 17:00–18:00 | 0 | 0 | 0 | 0 | 0 | 0 |